Operation Minerva

We performed a complete overhaul of a 3,150-tonne press, as well as the design and implementation of automation for unloading and customising the product.
We replaced the software, installed new energy-saving servo pumps and overhauled the plasticising chamber, reducing consumption by 40%.

Operation Apollo

We overhauled the software of a 2,300-tonne press for an African customer to optimise the machine’s performance.

Operation Phoenix

This was one of Icotech Automation’s most ambitious projects.
In 2007, a factory in northern Europe suffered a fire that destroyed a 4,000-tonne press. After ten years of exposure to the elements, in 2018, we were asked to revive the press from the wreckage.

It was only possible to recover the steel from the original press, requiring us to redesign many components from scratch. The result was a high-performance, energy-efficient press with an optimised electrical and hydraulic system, comparable to an electric press in terms of speed and consumption.

Operation Hercules

We managed the relocation of a 2,300-tonne press from the old factory to the new one, with the necessity to get the machine back into production as quickly as possible. The entire operation was completed in one week, from the start of dismantling to start-up at the other factory. Everything was done by crane truck as neither factory was equipped with overhead cranes.

Operation Mercury

We oversaw the revamping of a 5,500-tonne press for an overseas client to improve cycle time. We performed electrical, mechanical and software maintenance, improving the efficiency of the machine by over 30% by installing inverters and implementing other technical solutions. In one month of work, the cycle time was reduced by more than 250 seconds to less than 230 seconds in total.

Operation Neptune

We handled the disassembly, packaging, shipping and overseas reassembly of a 5,500-tonne press. During the project the client also requested installation of an automation cell with an anthropomorphic robot for unloading the press, as well as automatic product customisation.

The plant’s size presented significant logistical challenges. For disassembly, we used a 450-tonne crane and built load-bearing wooden crates to hold the platens, which weighed over 100 tonnes each. Transport by sea, which lasted over 60 days, required secure fastening and protection against corrosive weather conditions.

At the receiving site, we designed and built the pit to house the machine and used special equipment such as gantry cranes and hovercraft to transfer the heavy parts from one area of the factory to another.

This operation required precise management and detailed planning to ensure the project’s success, demonstrating our technical capabilities and industry experience.

Operation Volcano

A client commissioned us to build a new production site.
We installed eight presses, between 160 and 1,200 tonnes. For those presses we developed specific automations, and installed all the services for the factory (including the overhead crane, power supply system, cooling system and other ancillary systems).
In four months we started up production and in the following six months we optimised the process.

Operation Ceres

We were responsible for the design and construction of a production site for manufacturing plastic roof tiles from recycled materials.

Operation Vesta

We were asked to redesign the internal layout of a factory with the aim of maximising space, adding new presses and improving production.
In just three months, we relocated eight presses, ranging from 160 to 4,000 tonnes, and installed a new press in the resulting space.